A Bidders’ Day was held on 08 June 2007.
The Derbyshire BSF programme was advertised to the market in the Journal of the European Union (OJEU) on 30 July 2007.
On 12 November 2007 two bidders were shortlisted and they submitted initial bids on 10 March 2007.
Conditional Close of dialogue took place on 27 November 2008 and final bids were received on 2 December 2008.
Equitix Ltd were appointed as the Preferred Bidder on 2 January 2009.
Work started on site at The Bolsover, Heritage and Springwell Schools in April 2009.
The Final Business Case was submitted to Partnerships for Schools in June 2009 and approved in July 2009.
Financial Close was reached on 23/24 July.
Design work began with Netherthorpe, Stubbin Wood and Tibshelf Schools and Shirebrook Academy in July 2009,
Development work started with the three secondary schools in Wave 5 - Frederick Gent, Alfreton Grange, Swanwick Hall School and the two special schools – Alfreton Park Community Special School and Swanwick School and Sports College.